On October 19, the Jiangsu Provincial Development and Reform Commission issued an "Energy Conservation Review Opinion" (Su Fa Gai Neng Shen [2026] No. 119), granting in-principle approval for the energy conservation report of the High-End New Materials Project by Lianyungang Petrochemical Co., Ltd. (Project Code: 2511-320720-04-01-720967; valid until October 19, 2028).
On October 20, the No. 4 blending silo unit (comprising 8 silos in total) for the High-End New Materials Project was successfully hoisted into place. In advance of the operation, the project supervision team and all participating contractors conducted comprehensive technical and safety briefings—outlining the hoisting procedures, personnel responsibilities, potential risk points, and emergency response measures. They also performed thorough inspections of critical equipment, including cranes, rigging, and wire ropes, and provided on-site supervision throughout the entire hoisting process, ensuring the operation was completed successfully.
Project Name: High-End New Materials Project of Lianyungang Petrochemical Co., Ltd.
Location: The Petrochemical Industrial Base in the Xuwei New District, Lianyungang. The project is sited across two areas: one within Lianyungang Petrochemical’s existing main plant site, and the other on land reserved within the Green Chemical New Materials Industrial Park. Lianyungang Petrochemical’s facilities consist of the main plant site and the Green Chemical New Materials Industrial Park site; this project is distributed across both locations. It is being implemented in two phases: the first phase includes the construction of a polyethylene unit and a 1-butene unit, while the remaining units are slated for the second phase.
Implementing Entity: Lianyungang Petrochemical Co., Ltd. (a wholly-owned subsidiary of Satellite Chemical).
Total Investment: 7.8 billion RMB. Construction scope: A new 120,000 tonnes/year butadiene extraction unit, a 50,000 tonnes/year 1-butene unit, a 100,000 tonnes/year polyolefin elastomer (POE) unit, a 900,000 tonnes/year polyethylene unit (comprising two 450,000 tonnes/year production lines), and a 100,000 tonnes/year linear alpha-olefin (LAO) unit. The project also includes a full suite of supporting utility and environmental protection facilities, such as storage and logistics tank farms, circulating water systems, power and heat supply, wastewater treatment, waste gas treatment, and centralized control systems.